Our Timeline

2011
Nov 26 - Signed purchase agreement
Nov 29 - Meeting with Loan Officer
Dec 6 - Meeting to select flooring
Dec 13 - Signed structural change waiver and Meeting with Guardian
Dec 28 - Notification of pre-approval for loan

2012
Jan 2 - Made final selections
Feb 15 - Pre-Construction Meeting and walk through of lot
Feb 17 - PM receives permits
Feb 22 - Ground breaking!

Mar 15 - Lumber is delivered
Mar 19 - Framing begins
Mar 27 - Framing and roof are completed
Mar 30 - Electric and plumbing are run

Apr 2 - Guardian selections installed

May 7 - Tentative close date